A job requires 2,400 actual labour hours for completion and it is anticipated that there will be 20% idle time. If the wage rate is ₹10 per hour, what is the budgeted labour cost for the job?

CS Executive · Cost and Management Accounting · PYQS · June 2018
A job requires 2,400 actual labour hours for completion and it is anticipated that there will be 20% idle time. If the wage rate is ₹10 per hour, what is the budgeted labour cost for the job?
(A) ₹19,200
(B) ₹24,000
(C) ₹28,800
(D) ₹30,000

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).

Topics: Cost and Management Accounting