The total production cost to produce one unit of finished goods was ₹45. Direct materials were 1/3 of the total cost, and direct labour was 40% of the combined total of direct labour and direct materials. The cost for di

CS Executive · Cost and Management Accounting · PYQS · June 2018
The total production cost to produce one unit of finished goods was ₹45. Direct materials were 1/3 of the total cost, and direct labour was 40% of the combined total of direct labour and direct materials. The cost for direct materials, direct labour, and factory overhead was :
(A) ₹15, 18 & 12 respectively
(B) ₹15, 12 & 18 respectively
(C) ₹15, 16 & 14 respectively
(D) ₹15, 10 & 20 respectively

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).