__________ trace or link the cost of performing certain activities to cost objects in Activity Based Costing system.

CS Executive · Cost and Management Accounting · PYQS · December 2018
__________ trace or link the cost of performing certain activities to cost objects in Activity Based Costing system.
(A) Resource Drivers
(B) Cost Drivers
(C) Cost Pools
(D) Cost Objects

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).