Standard output for 10 hours is 240 units, Actual output in 15 hours is 396 units and wages rate is ₹80 per hour. The amount of gross wages under Emerson Efficiency Plan will be :

CS Executive · Cost and Management Accounting · PYQS · December 2018
Standard output for 10 hours is 240 units, Actual output in 15 hours is 396 units and wages rate is ₹80 per hour. The amount of gross wages under Emerson Efficiency Plan will be :
(A) ₹1,260
(B) ₹1,309
(C) ₹1,320
(D) ₹1,560

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).

Topics: Labour Costing