If standard output for 8 hours is 200 units and actual output in 10 hours is 350 units, the efficiency level will be :

CS Executive · Cost and Management Accounting · PYQS · December 2018
If standard output for 8 hours is 200 units and actual output in 10 hours is 350 units, the efficiency level will be :
(A) 175%
(B) 140%
(C) 57.14%
(D) 71.42%

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Labour Costing