The following are the data related to Job No. 102: Raw materials ₹21,000 Direct wages for 80 hours @ ₹150 per hour Factory overhead incurred for all jobs ₹4,80,000 for 4,000 hours. Factory cost of the Job No. 102 will be

CS Executive · Cost and Management Accounting · PYQS · December 2018
The following are the data related to Job No. 102: Raw materials ₹21,000 Direct wages for 80 hours @ ₹150 per hour Factory overhead incurred for all jobs ₹4,80,000 for 4,000 hours. Factory cost of the Job No. 102 will be :
(A) ₹33,000
(B) ₹42,600
(C) ₹51,300
(D) ₹22,020

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Job Costing