The Cost Accounting Standard related with pollution control cost is :

CS Executive · Cost and Management Accounting · PYQS · December 2019
The Cost Accounting Standard related with pollution control cost is :
(A) CAS 7
(B) CAS 10
(C) CAS 14
(D) CAS 19

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Cost Accounting Standards (CAS)

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject