Normal rate per hour ₹4.00; Piece rate ₹3.00 per unit; Standard 2 units per hour; In 40 hours, total production of the worker is 120 units. Calculate the earnings of the worker under Gantt's Task and Bonus Plan.

CS Executive · Cost and Management Accounting · PYQS · December 2019
Normal rate per hour ₹4.00; Piece rate ₹3.00 per unit; Standard 2 units per hour; In 40 hours, total production of the worker is 120 units. Calculate the earnings of the worker under Gantt's Task and Bonus Plan.
(A) ₹630
(B) ₹432
(C) ₹288
(D) ₹192

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Labour Costing

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject

Related Questions in this Topic