Normal rate per hour = ₹5.40; Standard time per unit = 1 Minute; Output per day = 450 units; Working hours per day are 8; Calculate the earning as per Merrick's Multiple Piece Rate System.

CS Executive · Cost and Management Accounting · PYQS · December 2019
Normal rate per hour = ₹5.40; Standard time per unit = 1 Minute; Output per day = 450 units; Working hours per day are 8; Calculate the earning as per Merrick's Multiple Piece Rate System.
(A) ₹40.50
(B) ₹44.55
(C) ₹55.44
(D) ₹35.10

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).