If an application is made under the Factories Act, 1948 for the approval of site for the construction or extension of the factory and required plans and specifications have been submitted by the registered post to the St

CS Executive · Industrial, Labour & General Laws · PYQS · December 2020
If an application is made under the Factories Act, 1948 for the approval of site for the construction or extension of the factory and required plans and specifications have been submitted by the registered post to the State Govt. or the Chief Inspector and if no reply is received within ............ from the date on which it is sent, the application stands automatically approved.
(A) 1 month
(B) 2 months
(C) 3 months
(D) 6 months

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Industrial Law