You are given the following data : Cost of machine ₹8,40,000 Estimated scrap value ₹40,000 Effective working hours 40,000 Hours worked during 4 weeks 300 Weekly repairs payment ₹500 Standing charges for 4 weekly period :

CS Executive · Cost and Management Accounting · PYQS · December 2020
You are given the following data : Cost of machine ₹8,40,000 Estimated scrap value ₹40,000 Effective working hours 40,000 Hours worked during 4 weeks 300 Weekly repairs payment ₹500 Standing charges for 4 weekly period : ₹4,000 Power consumed by machine : 10 units per hour @ ₹1.50 per unit Machine hour rate will be :
(A) ₹40.00
(B) ₹41.50
(C) ₹42.00
(D) ₹55

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).

Topics: Machine Hour Rate

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject