Match the following : (P) Maintenance | (1) Area department (Q) Welfare | (2) Value of department Materials (R) Stores-keeping | (3) Number of department Employees (S) Building service | (4) Hours department Worked (P) (
CS Executive · Cost and Management Accounting · PYQS · December 2020
Match the following : (P) Maintenance | (1) Area department (Q) Welfare | (2) Value of department Materials (R) Stores-keeping | (3) Number of department Employees (S) Building service | (4) Hours department Worked (P) (Q) (R) (S)
Answer & Explanation:
Correct Answer: Option (C)
Official answer key: (C).
Topics: Overheads
Related Questions in this Topic
- 27. Pre-determined factory overhead rate was ₹10 per labour hour. Actual labour hour worked 80,000. Actual factory overh...
- 19. Which of the following is not a method of segregation of semi-variable overhead costs into fixed and variable costs:
- 13. Regular maintenance expenses of factory buildings are:
- 12. Which of the following is not a method of cost absorption ?
- If prime cost is ₹17,80,000 and factory cost is ₹22,25,000, then absorption rate of factory overhead on prime cost is: