State the procedure for 'Approval of model' of weight or measures before its manufacture or import under the Legal Meteorology Act, 2009. Under what circumstances approval is not required?
CS Executive · Economic and Commercial Laws · PYQS · June 2021
State the procedure for 'Approval of model' of weight or measures before its manufacture or import under the Legal Meteorology Act, 2009. Under what circumstances approval is not required?
Answer & Explanation:
Every person, before manufacturing or importing any weight or measure shall seek the approval of model of such weight or measure in such manner, on payment of such fee and from such authority as may be prescribed. However, such approval of model may not be required in respect of any cast iron, brass, bullion, or carat weight or any beam scale, length measures (not being measuring tapes) which are ordinarily used in retail trade for measuring textiles or timber, capacity measures, not exceeding twenty litre in capacity, which are ordinarily used in retail trade for measuring kerosene, milk or potable liquors. It may be noted that the prescribed authority may, if he is satisfied that the model of any weight or measure which has been approved in a country outside India conforms to the standards established by or under this Act, approve such model without any test or after such test as he may deem fit.
Topics: Legal Metrology Act, 2009
Related Questions in this Topic
- Discuss the powers of Legal Meteorology officer regarding inspection and seizures under the Legal Meteorology Act, 2009.
- Define the term 'Manufacturer' as used in Legal Meteorology Act, 2009.
- Discuss the powers of Legal Metrology Officer regarding inspection and seizure under Legal Metrology Act, 2009.
- "Every non-standard weight and measure used in the course of trade is liable to be forfeited". Comment.
- What are the provisions of the Legal Metrology Act, 2009 relating to declarations on pre-packaged commodities?