Decision rules based on Benefit Cost Ratio (BCR) and Net Benefit Cost Ratio (NBCR) criteria implies:

CS Executive · Financial and Strategic Management · PYQS · December 2019
Decision rules based on Benefit Cost Ratio (BCR) and Net Benefit Cost Ratio (NBCR) criteria implies:
(A) If BCR < 1, accept the project
(B) If NBCR < 0, accept the project
(C) If NBCR > 0, reject the project
(D) If BCR < 1, reject the project

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).

Topics: Financial Management