If the cut off rate of a project is lower than IRR, we may:

CS Executive · Financial and Strategic Management · PYQS · June 2021
If the cut off rate of a project is lower than IRR, we may:
(A) Accept the proposal
(B) Reject the proposal
(C) Be neutral about it
(D) Wait for the IRR to increase and match the cut off rate

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).

Topics: Capital Budgeting