In Activity Based Costing (ABC), __________ is a factor that causes a change in the cost of an activity.

CS Executive · Corporate and Management Accounting · PYQS · December 2022
In Activity Based Costing (ABC), __________ is a factor that causes a change in the cost of an activity.
(A) Cost object
(B) Cost driver
(C) Cost pool
(D) Cost unit

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Cost Accounting