Which of the following is not a type of Feasibility Studies conducted during primary stage of a project financing to undertake a macro view of project ?

CS Executive · Financial and Strategic Management · PYQS · June 2024
Which of the following is not a type of Feasibility Studies conducted during primary stage of a project financing to undertake a macro view of project ?
(A) Market Feasibility
(B) Environmental Feasibility
(C) Technical Feasibility
(D) Financial Feasibility

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Financial Management