When operating under a single-period capital-rationing constraint, you may first want to try selecting projects by descending order of their __________ in order to give yourself the best chance to select the mix of projects that adds most to the firm value.
(A) Profitability Index (PI)
(B) Net Present Value (NPV)
(C) Internal Rate of Return (IRR)
(D) Payback Period (PBP)

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).