Budgeted Hours = 1,25,000 Actual Production = 20,000 Standard hours per unit = ₹ 5 Actual hours = 90,000 Activity ratio is:

CS Executive · Corporate and Management Accounting · PYQS · June 2024
Budgeted Hours = 1,25,000 Actual Production = 20,000 Standard hours per unit = ₹ 5 Actual hours = 90,000 Activity ratio is:
(A) 80%
(B) 125%
(C) 90%
(D) 111.11%

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).

Topics: Management Accounting