A project has expected NPV of ₹ 1,83,000. Its coefficient of variation is 0.07377. Risk free rate is 8% and cost of capital is 10%. What is the standard deviation of project ?

CS Executive · Financial and Strategic Management · PYQS · December 2024
A project has expected NPV of ₹ 1,83,000. Its coefficient of variation is 0.07377. Risk free rate is 8% and cost of capital is 10%. What is the standard deviation of project ?
(A) ₹ 15,000
(B) ₹ 12,000
(C) ₹ 13,500
(D) ₹ 13,334

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).